In low-rise and industrial workshops, calendar plans for the installation of sanitary and technical work are drawn up taking into account the end in the black work, after the installation of technological equipment, but before the finishing work.
Features of the preparation of calendar plans for the installation of sanitary work in buildings with brick walls and prefabricated reinforced concrete ceilings are that work can only be carried out if there are two ceilings over the head of the installers; In shameless buildings, laying the turning is carried out to the installation of the floor of the first floor.
Example. Build a calendar plan for heating and ventilation of the workshop, if the directive installation period is 10-15 days.
Solution. Based on the volume of work, we make calculation for installation work on heating and ventilation of the workshop. According to the calculation, labor costs were received: by heating – 144.4 people. DN., in ventilation –133.2 people. DN.
2. We determine the number of workers in the brigade: by heating
3. We make a calendar plan and the schedule of the labor force (rice. 278);
4. We make a brief explanatory note.
5. We determine the technical and economic indicators by the method specified in § 165.